Mine Spoils Leach Pad

Sequoia was awarded the contract to construct a 27 acre containment for potentially acid generating mine spoils for a confidential client in the Southeastern United States. The containment cell construction required close coordination with the Owner’s mining operations to ensure the containment capacity was prepared in time to support mining operations. In addition, the Owner coordinated the installation of geomembrane liner and permitting and initial filling of a wetland area that impacted about half of the work area.

Sequoia began the project by filling areas of the cell to subgrade while the Owner placed rock in the wetland area. Sequoia imported 430,000 cubic yards of material from several onsite sources that was used as structural fill, clay liner and protective cover materials. Once the 1.2 million square feet of low permeable soil liner was constructed, the Owner coordinated the placement of geomembrane liner so that Sequoia could continue to install 9,200 linear feet of underdrain piping and complete the placement of a 2 foot protective cover layer over the geomembrane. The total project was completed in 7 months.

Location

Southeastern US

Type of Project

Mining

Ready to get started?

Contact us to harness the expertise of our skilled team and cutting-edge equipment. Together, we’ll pave the way to your project's success.

More Projects

Inactive Basin Excavation

Environmental/CCR

Inactive Basin Excavation

Brunswick Nuclear Slope Stabilization

Shoreline Stabilization

Intake Canal Slope Stabilization

HF Lee Inactive Basins Dam Stabilization

Dams

Inactive Basins Dam Stabilization